AV facilities

Project ID: 
119
Current stage: 
Manager: 
Unit: 
What: 

Description: The installation of the AV facilities within the Forum needs to be completed, including providing appropriate documentation and training.

Deliverables: Both user and technical documentation. Training for support staff. Fully functional AV facilities as per agreed specification.

Why: 

Customer: All potential users of the AV facilities.

Case statement: We have a commitment to provide and support adequate AV facilities within the Forum.

When: 

Status:

Timescales:

Priority: CRUCIAL

Time:

How: 

Proposal:

Resources:

Plan:

Other: 

Dependencies: Original contractors require to complete some work.

Risks:

Milestones

Proposed date Achieved date Name Description
2011-05-29 Documentation Provide both user and technical documentation - as up to date as possible - awaiting completion by Mediascape.
2011-05-22 Mediascape Mediascape to complete outstanding work in G07/G07A
2009-05-29 2009-05-29 label ports All active ports in meeting rooms to be labelled.
2009-05-29 wireless keyboa Install wireless keyboards/mice for use with DICE machines in meeting rooms.