Description: The school database will be changing the feeds it gives us. There'll be some prometheus work to cope. Initially we will be getting a 3G feed of new and current PGR cohort. Note 21/01: this work is currently in progress (as driven by rollout on 10/01/11).

Deliverables: Working account management with revised DB.

Why: 

Customer:

Case statement: Has to be done if we want to keep working with the revised DB.

When: 

Status:

Timescales:

Priority:

Time: Probably 2-3 weeks, but dependent on issues discovered.

How: 

Proposal:

Resources:

Plan: Currently in progress, as indicated above. Plan is:

  • Write new prometheus store/conduit for new feed. done
  • Testing/data integrity checking of conduit. in progress
  • Roll out to live server
  • RAT to provide combined feed of 2g/3g data
  • Adapt conduits for new feed
  • Testing of new feed
  • Rollout
Other: 

Dependencies: See also devproj #169.