Infrastructure for Appleton Tower Refurbishment

Project ID: 
26
Current stage: 
Manager: 
Unit: 
What: 

Description: Ensure that the network infrastructure is in place for the ongoing Appleton Tower refurbishment.

Deliverables: A working network in the refurbished AT floors.

Why: 

Customer: School.

Case statement: Various floors of AT are being refurbished. We have to ensure that there's network provision for when they're reoccupied.

When: 

Status: Upper floors done. We're moving to the basement next...

Timescales: Timeline determined by Works/contractors.

Priority: High.

Time:

How: 

Proposal:

Resources:

Plan:

Other: 

Dependencies: Timeline determined by Works/contractors.

Risks:

Milestones

Proposed date Achieved date Name Description
2007-03-30 2007-02-23 AT678Kit Specify network kit for refurbished floors.
See the
corresponding RT ticket
for details.
2007-06-22 2007-06-18 AT34Kit Re-evaluate AT3/4 kit for future reuse when we reoccupy the floors.
2007-09-10 2007-08-27 at34Ready Occupy AT3/4. This is the contractor's deadline, as set by the AT planning meeting.
2007-11-12 2007-12-01 ATbPlanning Initial planning for AT basement refurbishment
2008-11-14 2008-10-31 SRdecant Start of decant period out of basement server room
2009-04-27 2009-04-18 SRcontractorsIn Contractors start work on the AT basement server room
2010-01-31 2009-08-14 SRdone AT basement server room should be ready for reoccupation