You are here
Prometheus: migration to new database feeds
Fri, 01/25/2013 - 15:46 - boss
Project ID:
187
Current stage:
Manager:
Unit:
What:
Description: The school database will be changing the feeds it gives us. There'll be some prometheus work to cope. Initially we will be getting a 3G feed of new and current PGR cohort. Note 21/01: this work is currently in progress (as driven by rollout on 10/01/11).
Deliverables: Working account management with revised DB.
Why:
Customer:
Case statement: Has to be done if we want to keep working with the revised DB.
When:
Status:
Timescales:
Priority:
Time: Probably 2-3 weeks, but dependent on issues discovered.
How:
Proposal:
Resources:
Plan: Currently in progress, as indicated above. Plan is:
- Write new prometheus store/conduit for new feed. done
- Testing/data integrity checking of conduit. in progress
- Roll out to live server
- RAT to provide combined feed of 2g/3g data
- Adapt conduits for new feed
- Testing of new feed
- Rollout
Other: