Introduce a Production FC5 Desktop

Project ID: 
27
Current stage: 
Manager: 
Unit: 
What: 

Description:

Create a production quality FC5 Desktop for staff and lab machines. This is a subproject of the FC5Upgrade

At the start of the development process FC5 was the current fedora core product and the logical base for the next version of DICE.

Deliverables: A production service running on lab and staff machines. Suitable Documentation for the system to be managed day to day by the support unit and to provide a gentle introduction for new users.

Why: 

Customer: Everyone

Case statement: It's part of the annual upgrade program and needed to support new hardware.

When: 

Status:

Timescales: The Dekstop needs to be ready in order to deploy in labs and on staff desktops for the start of term^h^h^h^h semester (18th September)

Priority: high

Time:

How: 

Proposal: Deploy on all desktops.

Resources: This is a large scale project and will require wide cross team resources.

Plan:

  1. Produce bugzilla list of rpms needing updating
  2. Produce bugzilla list of desktop checklist.
  3. Deploy test machines for staff to check hardware
  4. Deploy on C(S)O's desktops
  5. Once we have an acceptable base we can work from start installing in labs
  6. Once we have a working desktop start deploying to selected staff.
  7. Beta test and polish.
  8. Site wide deployment.
Other: 

Dependencies: FC5 has to ship.....it did.

Risks: We need to have a working desktop.

URL:https://wiki.inf.ed.ac.uk/DICE/Fc5DesktopDevelopmentPlan

Milestones

Proposed date Achieved date Name Description
2006-06-15 2006-05-15 1 Produce bugzilla list of rpms needing updating
2006-06-15 2006-05-15 2 Produce bugzilla list of desktop checklist.
2006-06-15 2006-05-15 3 Deploy test machines for staff to check hardware
2006-08-31 2006-06-15 4 Deploy on C(S)O's desktops
2006-11-03 2006-07-30 5 Once we have an acceptable base we can work from start installing in labs
2006-08-01 2006-08-01 6 Once we have a working desktop start deploying to selected staff.
2006-12-01 2006-11-08 7 Beta test and polish.
2007-05-23 2007-03-01 Final deploymen Site wide deployment.
2007-08-01 2007-07-01 report write up report on the project.
writeup is here