Description:
Create a production quality FC5 Desktop for staff and lab machines. This is a subproject of the FC5Upgrade
At the start of the development process FC5 was the current fedora core product and the logical base for the next version of DICE.
Deliverables: A production service running on lab and staff machines. Suitable Documentation for the system to be managed day to day by the support unit and to provide a gentle introduction for new users.
Customer: Everyone
Case statement: It's part of the annual upgrade program and needed to support new hardware.
Status:
Timescales: The Dekstop needs to be ready in order to deploy in labs and on staff desktops for the start of term^h^h^h^h semester (18th September)
Priority: high
Time:
Proposal: Deploy on all desktops.
Resources: This is a large scale project and will require wide cross team resources.
Plan:
- Produce bugzilla list of rpms needing updating
- Produce bugzilla list of desktop checklist.
- Deploy test machines for staff to check hardware
- Deploy on C(S)O's desktops
- Once we have an acceptable base we can work from start installing in labs
- Once we have a working desktop start deploying to selected staff.
- Beta test and polish.
- Site wide deployment.
Dependencies: FC5 has to ship.....it did.
Risks: We need to have a working desktop.
URL:https://wiki.inf.ed.ac.uk/DICE/Fc5DesktopDevelopmentPlan
Milestones
Proposed date | Achieved date | Name | Description |
---|---|---|---|
2006-06-15 | 2006-05-15 | 1 | Produce bugzilla list of rpms needing updating |
2006-06-15 | 2006-05-15 | 2 | Produce bugzilla list of desktop checklist. |
2006-06-15 | 2006-05-15 | 3 | Deploy test machines for staff to check hardware |
2006-08-31 | 2006-06-15 | 4 | Deploy on C(S)O's desktops |
2006-11-03 | 2006-07-30 | 5 | Once we have an acceptable base we can work from start installing in labs |
2006-08-01 | 2006-08-01 | 6 | Once we have a working desktop start deploying to selected staff. |
2006-12-01 | 2006-11-08 | 7 | Beta test and polish. |
2007-05-23 | 2007-03-01 | Final deploymen | Site wide deployment. |
2007-08-01 | 2007-07-01 | report | write up report on the project. writeup is here |